Latest pics and update from Blackwell Meadows

By Ray Simpson

Latest pics and update from Blackwell Meadows

Our snapper, Nick visited Blackwell Meadows earlier in the week and took these images, and Malcolm,...

Our snapper, Nick visited Blackwell Meadows earlier in the week and took these images, and Malcolm, our project manager, has provided the words.

Work has now commenced on the new Car park with topsoil stripped and the exit point formed. Progress should be on schedule - weather permitting.

The Changing Rooms are ready to receive their roof covering which will then facilitate internal fitting out. Internal alterations to the existing Changing Rooms are also progressing to create Changing Facilities for the Referee's team and for the new Clubhouse Entrance on the North elevation.

The Tin Shed structure is complete awaiting installation of crash barriers along the front edge and on either end as per the terraced Stand at Heritage Park.

The seats for the Seated Stand have arrived on site and are being installed today.

Pitch perimeter fencing is near complete with the last section in front of the Tin Shed being progressed this week. This will be followed by completion of the perimeter paving.

Bases are in place for the Home and Away Turnstile units which are due on site next week, followed by the Spectator Toilet units and completion of the enclosing fencing and gates at the two main entrances.

 

Blackwell Meadows update-1

 

Blackwell Meadows update-2 Blackwell Meadows update-3 Blackwell Meadows update-4 Blackwell Meadows update-5 Blackwell Meadows update-6

Blackwell Meadows update-7